Go to the SmartLink Folder in the Tree View and open the SmartLink folder. Click All Light Schedules. In the List view, right click and choose New. | Go to the SmartLink Folder in the Tree View and open the SmartLink folder. Click All Light Schedules. In the List view, right click and choose New. | ||
− | From here you can | + | From here you can specify details for the schedule by define on/off times to light your faces. Use the Schedule type combo box to choose whether the schedule has no lights, one periods or two periods of lighting. Specify the on and off times for the period(s) of lighting. Give the schedule a meaningful name and code. Finally, click Save to create the schedule. |
− | + | ||
− | + | ||
[[File:SmartLinkNewSchedule.png]] | [[File:SmartLinkNewSchedule.png]] |
Revision as of 15:10, 25 May 2016
The SmartLink module allows you to send lighting control commands to the SmartLink system, allowing you to have default lighting schedules for faces, as well as lighting control schedules for campaigns.
Contents |
Initial Setup
Go to Tools-Options-SmartLink.
From this screen you can enter the license information that allows you to connect to the SmartLink system. You can enter your license key (provided by OutdoorLink), along with the specified User id and password. You can test your connection by clicking the Test button to ensure the information has been successfully entered.
Next, set up the default light schedule you wish to apply to faces in Ad Manager. Note this will only take effect if you have specified the SmartLink details for the Face, but have not supplied a light schedule to follow.
Once you have entered the appropriate information, click OK.
Creating Light Schedules
Go to the SmartLink Folder in the Tree View and open the SmartLink folder. Click All Light Schedules. In the List view, right click and choose New.
From here you can specify details for the schedule by define on/off times to light your faces. Use the Schedule type combo box to choose whether the schedule has no lights, one periods or two periods of lighting. Specify the on and off times for the period(s) of lighting. Give the schedule a meaningful name and code. Finally, click Save to create the schedule.
Assigning Light Schedules to Faces
When assigning a light schedule to a Face, you can either do this one face at a time, or multiple faces at a time.
Single Face
To update a single face with a lighting schedule, go to the Face and go to the SmartLink tab. From this tab you can mark the face as having its lighting controlled by SmartLink. After you have done this, you can select the default light schedule to apply to this Face. If you leave the Light Schedule blank, the Default schedule set under Tools-Options will be used.
The next step is to identify the Plant, Structure and Panel information provided by OutdoorLink for this Face. Once this information has been entered, click Save. Please note that if this information is not entered correctly, Ad Manager will not be able to send the lighting schedule information to the SmartLink controller.
Multiple Faces at a Time
If you wish to update multiple faces at a time, highlight the faces, right click and select Update Light Schedule. You can click the check box below SmartLink Enabled and change the value to "Yes" and you can specify the default light schedule for these faces. If you leave the Light Schedule blank, the Default schedule set under Tools-Options will be used.
Please note that after you have updated these faces via this tool, you will still need to visit each face to enter its SmartLink credentials as described under the Single Face methodology.
Assigning Light Schedules to Subcontracts
Ad Manager allows you to specify a specific light schedule to use for a campaign, if desired.
If you wish to use this feature, open the Subcontract and click on the SmartLink tab. Select the light schedule to be applied to all SmartLink controlled faces on this Subcontract. This lighting schedule will override the default schedule. If a light schedule is not applied to a Subcontract, the default schedule for each Face will be used. Click Save after you have selected the desired schedule.
If you wish to update multiple Subcontracts with the same lighting schedule, highlight the Subcontracts in a List View, right click and select Update Light Schedule. Click the check box, choose the desired light schedule, then click OK.
Publishing Light Schedules to SmartLink
Manually
If you wish to send all lighting schedules to SmartLink immediately, go to Tools-SmartLink-Publish SmartLink Schedules. Additional options will be available to allow you to turn off lights for expired postings and whether to re-send all light schedules.
Click Ok to proceed, and progress information for each face and on completion will appear with a summary of the results. Log entries are also displayed.
To send schedule for a single face, open the Face and run Tools-Publish Lightschedule.
Scheduled
A scheduled task can be configured to run daily to update light schedules after your day's postings have been entered into Ad Manager as completed. Log entries can be viewed for results of publishing.